8 Network Data Return

8.1 POLLUTION YEAR CALENDAR

The Network is operated according to a long-established "Pollution Year calendar". The Pollution Year always begins on the Tuesday nearest to 1st April, and contains twelve months, each of exactly 4 or 5 weeks, all beginning on Tuesdays (to minimise problems with public holidays, which often occur on Mondays). The months are arranged to correspond as closely as possible to calendar months. Weeks are numbered. The year is divided into "summer" (April to September) and "winter" (October to March). Data from the Network are processed in batches corresponding to one Pollution Calendar month, and the site operators receive a monthly printout of results.

8.2 DATA RETURN FORM

In order to ensure that all site operators send their results for processing in a consistent format, a standard data return form is used. These pre-printed forms, are issued monthly by AEA Technology Environment. The data return form is two-sided. The front is for data entry, the back contains instructions for completion; the front and back are shown in Fig. 8.1 and 8.2 respectively.

The form should be completed according to the instructions on the back. Please do your best to return your completed forms within 2 weeks of the end of the month shown at the top of the form, and no later than 4 weeks after the end of the month. Forms arriving later than this will have to be processed separately, and it could be several months before you get the results printouts.

If at all possible, the operator should take the Data Return Form to the sites when they are visited, and record the gas meter reading directly onto the form. Likewise, titration results and reflectometer readings should be recorded on the form at the time these measurements are made. This avoids transcription errors. However, if this is not possible, a log book should be kept in which the above data can be recorded. All entries should identify the site and date. The log book should be used for this purpose only, and great care should be taken when results are copied onto the form.

8.3 POINTS TO NOTE

Please bear the following points in mind when completing the form:

Meter readings & times

New Meters

Reflectometer Readings

Titration Results

8.4 COMMON ERRORS

Certain errors occur frequently; these are listed below.

8.5 DATA REQUIRED FOR CALCULATIONS

Certain criteria have been adopted in the computer validation program so that no calculations can be carried out when the results would, in effect, be meaningless. The main safeguards are as follows;

Also, the following occurences are highlighted for attention, as they may indicate an error or a problem:

8.6 CONTINUITY OF MONITORING: BREAKDOWN OF EQUIPMENT

AEA Technology Environment are committed to maximising data capture from the UK Smoke and SO2 Network, and the efforts made by site operators to avoid breakdowns are greatly appreciated. Regular maintenance, and weekly checks of sampling flowrate reduce the likelihood of breakdowns and provide early warning of problems before they become serious. It is useful to keep spare components if possible; in particular, if a Capex pump is in use, the site operator should keep a spare filter and critical orifice assembly to hand. If an equipment breakdown occurs, please fill in the data return form as instructed on the back.

It is also greatly appreciated if measurements can be kept up over the Christmas holiday when heavy pollution is not unusual. It is usually possible to make an extra site visit before the holidays, so that unattended periods of more than 7 days can be avoided.

Figure 8.1 Smoke and Sulphur Dioxide Data Return Form: Front

Figure 8.2 Smoke and Sulphur Dioxide Data Return Form: Back
Site prepared by the National Environmental Technology Centre, part of AEA Technology, on behalf of the UK Department of the Environment, Transport and the Regions